The Harlington's renovation has gone in for planning and the lease on its shopping centre stand-in is signed. A builder should be picked in early January.
The planning application to renovate The Harlington went in to Hart District Council on Friday 30 October. Fleet Town Council has also signed the lease on the shopping centre unit that will stand in while the building is shut.
Both steps were reported to the full council on 4 November. The minutes say the architects, Burrell Foley Fischer (BFF), submitted the application and that Hart “acknowledged receipt on Monday and issued an invoice for the planning application fee”. The lease for the shopping centre unit “had now been signed by all parties”. (Fleet Town Council, minutes, 4 November 2026)
A month ago the lease was stuck. On 7 October councillors heard it was with the landlord’s solicitors in Hong Kong, and design work on the temporary venue was on hold until it was agreed. Our story on the closure has the background.
Not on the register yet
The application had not appeared on Hart’s public planning register when we searched it on 10 November. A search for The Harlington’s address, 236 Fleet Road, returned only applications from the 1950s to the 1980s. Applications usually appear once the council has validated them, and that is when the public can comment.
We will add the reference and the comment deadline when it is published. Our Fleet planning news page will carry it too.
Choosing a builder
The council is hiring a management contractor to run the build. The minutes give this timetable:
- 21 November: deadline for builders to prequalify. The documents were published on the government’s procurement portal
- 23 November: the Stage 1 tender is due to open
- 18 December: the tender closes
- early January 2027: the successful builder is expected to be appointed
The chairman told councillors there “remained some uncertainty as to whether this timetable was achievable”. The project manager, Synergy, will update the overall programme once the tender dates are confirmed. Interest from builders “appeared encouraging”, the minutes say.
The design is about two months behind
The chairman met Synergy on 8 October to review the programme. His report says the detailed design, RIBA Stage 4, “is running about 2 months late”.
The main cause was that the move into the temporary venue had been put on the project’s critical path. That meant the whole programme waited on it. The council agreed to remove that link, which “improved overall programme”.
It also agreed that BFF should finish the Stage 4 design before handing it to the builder. BFF’s team was back on site on 15 October, including in the roof voids, looking at the structure, access and materials. The chairman reported that fire safety and accessibility issues had been resolved.
The minutes do not say whether the expected closure from around February 2027 has moved. The last show on sale in the building is still 80s Rewind: One Last Dance on Saturday 30 January. (The Harlington box office)
The shopping centre unit
The council calls the temporary programme Harlington on Tour. It will run from a unit in the Hart Shopping Centre, which the architects’ Stage 2 report names as the former M&Co store.
Now that the lease is signed, design work on it has restarted. BFF has sent in preliminary layouts. Engineers from Skelly & Couch spent a day at the unit recording its mechanical and electrical equipment. Their report will set out what work the change of use needs, including air circulation and electrical capacity.
Councillors know the temporary venue carries risk. At the Policy and Finance committee on 21 October they named the Harlington Development and Harlington on Tour budgets as “the principal areas of financial risk” in next year’s draft budget. They said the Harlington on Tour assumptions “required detailed review” and set up a working group to do it. The committee also agreed a monthly working group on The Harlington’s operations and finances. (Policy and Finance minutes, 21 October 2026, in the 4 November pack)
The new venue also has to be added to the council’s risk register. Councillors agreed on 4 November that the register needs updating for the venue “now that the lease has been signed”, and for the main project’s construction costs and financing once Stage 4 is complete.
Fleet Library’s heating
Fleet Library, run by Hampshire County Council, shares the building and its boilers. The county had planned to get its own heating before the renovation. That has run into trouble.
The chairman met the county’s library service online on 21 October. His report says the county’s plans “to become independent of the Harlington boilers has encountered planning and technical problems significantly delaying the project”. The county was “exploring the potential for the heating to be left on through this coming winter period”.
In September The Harlington’s general manager told councillors the building was running on one working boiler. (Recreation, Leisure and Amenities minutes, 16 September 2026)
The minutes do not say what happens to the library’s heating once The Harlington closes for the building work.
What it means for you
- Shows and hires in the old building run to the end of January. The last night listed is Saturday 30 January 2027.
- Watch for the planning application. Once Hart validates it, anyone can comment on the register. We will publish the reference and the deadline.
- Library users: nothing has changed yet, and the county is looking at keeping the heating on this winter.
- Council tax: the town council’s 2027/28 budget goes to the full council on Wednesday 2 December at 7pm at The Harlington. The precept may be set in January instead. Our Fleet council tax bands page has the full bill.
Sources
- Fleet Town Council, full council minutes, 4 November 2026, for the planning application, the lease, the procurement timetable, the Stage 4 delay, the library heating and the risk register.
- Fleet Town Council, full council pack, 4 November 2026, for the Policy and Finance committee minutes of 21 October.
- Fleet Town Council, minutes, 7 October 2026, for the earlier lease delay.
- Hart District Council, planning register, searched 10 November 2026.