The Harlington in Fleet shuts completely from about February 2027 for a 68-week renovation. The last show listed is 30 January; a shopping centre unit stands in.
Updated 10 November: the planning application went in to Hart on 30 October and the lease on the shopping centre unit has been signed. A builder is expected to be appointed in early January. Full story.
The Harlington, Fleet’s arts centre and town council base, will close completely from around February 2027 so its renovation can start. Fleet Town Council puts the building work at 68 weeks.
The dates are in a budget paper to the full council on 7 October. It says the current project plan “anticipates a full closure of The Harlington from around February 2027” and that “no part of the existing building is expected to remain operational” while the work goes on. (Fleet Town Council, meeting pack, 7 October 2026)
Some shows and hires will move to a temporary home in the Hart Shopping Centre. The lease for it had still not been signed on 7 October; it was signed by early November.
The last nights before the doors close
The venue’s own box office lists its final run in late January. The last night on sale is 80s Rewind: One Last Dance on Saturday 30 January 2027, with tickets at £24. The listing reads “Before the doors close… we rewind” and says the venue will then “take the party on tour”. (The Harlington box office)
The other January dates on sale are:
- Stand Up for Saturday Comedy Club, Saturday 16 January
- DC/UK, the AC/DC tribute, Friday 22 January
- Cheesy Bingo Party, Saturday 23 January
- Tinderella, an adult pantomime, two shows on Friday 29 January
Before that, the pantomime goes ahead as normal. Aladdin runs from 11 to 29 December; times and prices are on our Fleet pantomime and Christmas shows page.
The box office is already selling a few dates from June 2027 onwards, still under The Harlington’s name. The listings do not say where those shows will be held.
Christmas Day lunch stays, with a cold menu
Fleet Town Council’s free Christmas Day event, for people in Fleet, Church Crookham and Elvetham Heath who would otherwise be alone, will still be held at The Harlington. It runs from noon to 4pm on 25 December.
The menu changes this year. The council says that “to prepare for the building closing for refurbishment, and our move to a temporary venue (without the same facilities)”, it will try a “cold but still festive menu”. Guests can book on 01252 625246 or at info@fleet-tc.gov.uk. (Fleet Town Council, Christmas Day event)
The two charities based in The Point, part of the building, are expected to move out in December. They are Fleet Phoenix and Sasha’s Project, according to the same budget paper.
Where The Harlington goes in the meantime
The council is taking a unit in the Hart Shopping Centre. The architects’ Stage 2 report names it as the former M&Co store, and says the aim is to keep the organisation “visible to patrons during the main building’s dark period”. (Burrell Foley Fischer, RIBA Stage 2 report, part 1)
It is not a like-for-like swap. The report lists problems still to be solved in the unit:
- its many columns, which seating and staging have to work around
- toilets, because the public WCs sit apart on the shopping centre concourse
- noise, with separation from neighbouring shops “likely to be a particular area of focus”
- fire safety, which will set how many people the space can hold
The lease is not done. At the 7 October meeting, councillors heard that the council had sent back the approved lease more than two weeks earlier. It had then gone to the landlord’s in-house solicitors, in Hong Kong, and the lease plan was still not agreed. Design work on the temporary venue was on hold until it is. (Fleet Town Council, minutes, 7 October 2026)
The budget paper warns that the delay “has inevitably limited” what the general manager can book for 2027/28. It says there is a risk the programme “will be less extensive than in a normal year”. It also says nobody yet knows “whether existing Harlington audiences will follow the programme to the temporary venue”.
What the renovation will change
Residents chose the cheapest of three options in a vote that closed on 15 November 2025. Of 2,044 votes, 1,909 were valid and 51% backed Option A, which the council said could be paid for within its existing share of council tax. (Fleet Town Council, Harlington Renovation)
The council’s project page says every option includes:
- an upgraded auditorium with retractable tiered seating
- new balcony seating to increase capacity
- complete replacement of the heating and electrical systems
- wall and roof insulation and double glazing
- new toilets, floors, ceilings, doors and windows
- a new front and a better way into the building
The Stage 2 design, dated 17 February 2026, adds more seats. The auditorium holds 316 seated today. The design takes that to 358 seats plus six wheelchair spaces. Standing gigs go from 500 to 591, and cabaret layouts from 282 to 344.
Some things will not come back. A later addendum, dated 1 September, records the council’s decision “to not reinstate the kitchen”. Instead there will be space to reheat food brought in by outside caterers. (Stage 2 report addendum)
Heating will stay on gas. At the residents’ meeting in March, the council said one reason was that electricity currently costs more than gas. New pipework, radiators and pressure vessels are going in so heat pumps can be added later, and the new roof will allow solar panels. (Annual residents’ meeting minutes, 10 March 2026)
The work cannot come soon enough for the current building. In September the general manager told councillors The Harlington was running on one working boiler. (Recreation, Leisure and Amenities minutes, 16 September 2026)
The cost, and how it will be paid for
The council has not published a total cost. Its finance report for the quarter to 30 September says the Stage 3 design “identified an increase in estimated construction costs”. A value engineering exercise “mitigated, rather than completely eliminated, the increase”. The detail of those cuts was agreed in private on 4 August. (Policy and Finance meeting pack, 21 October 2026)
The project is being paid for with:
- a loan from the Public Works Loan Board, the government lender to councils
- the council’s reserves, which hold £3,292,505 in a Harlington Development Fund
- Section 106 money from developers
The first draft of next year’s budget assumes £7.2m of borrowing in 2027/28. This year’s budget had pencilled in £8.384m. The note beside the line says interest rates “have gone up, can borrow less for same repayment value”. On 1 September the rate for a 40-year loan was 6.82%, and the council does not need to draw the money down until early 2027. (Full council minutes, 2 September 2026)
The draft also takes £3.3m from reserves and £400,000 of Section 106 money. The council is choosing a builder through an open tender on Find a Tender. A planning application was described on 7 October as ready “imminently”.
What it means for your council tax
Fleet Town Council’s share of a Band D bill would rise from £139.47 to £150.05 in 2027/28 under the first draft budget. That is £10.58 a year, or 7.59%.
The vote leaflet said Option A “can be done within the existing Fleet Town Council element of your council tax”. The draft does not carry a line for the renovation itself. Its biggest added costs are:
- inflation and minor adjustments, £61,962
- lost interest as reserves are spent on the project, £47,000
- a net fall in Harlington income during the closure, £41,800
- higher business rates, £17,640
Against that, it saves £58,180 on Harlington gas, electricity and water while the building is shut. The draft goes to the Policy and Finance committee on Wednesday 21 October. Councillors noted on 7 October that the precept may be set in January rather than December.
This is the town council’s part of the bill only. Hart District Council, Hampshire County Council, the police and the fire service set theirs separately; our Fleet council tax bands page has the full Band A to H figures.
What it means for you
- Book now for anything you want to see in the old building. The final night listed is Saturday 30 January 2027.
- If you hire a room or run a regular class there, ask the council now what can move to the shopping centre unit. The programme there is expected to be smaller.
- Come to the Policy and Finance meeting on Wednesday 21 October at 7pm, in the Function Room at The Harlington, if you want to hear the draft budget discussed. Members of the public can speak for up to three minutes.
- Watch for the planning application on Hart District Council’s register. Our Fleet planning news page will carry it when it goes in.
- Christmas Day lunch guests can still book on 01252 625246.
Have your say