Work has started on a £1.5m upgrade of Fleet Community Hospital, with new therapy, gym and group space for physio clinics. It is due to finish by March 2027.
Work has started on a £1.5 million refurbishment of Fleet Community Hospital, which will make room for more physiotherapy, community nursing and outpatient appointments in the town.
Frimley Health NHS Foundation Trust, which runs the hospital, says the work is targeted for completion by the end of March 2027.
Overview
- What: a £1.5 million redevelopment of Fleet Community Hospital
- What changes: reception, clinical and staff areas; electrical and digital systems; new therapy, gym and group space; extra parking being planned
- When: work has just started, with completion targeted for the end of March 2027
- Will the hospital stay open? Yes. The trust says the work is phased so clinical services can continue throughout
What the money pays for
The trust says the investment will improve the reception, clinical and staff areas, upgrade the hospital’s electrical and digital infrastructure, and create additional therapy, gym and group space.
“Improvements to access, including additional parking, are also being planned,” the trust said.
Its stated aim is “to create more capacity for physiotherapy, community nursing and outpatient services, enabling more patients to receive care closer to home.”
Who is paying
Most of the funding came from NHS England’s elective recovery funding, the trust said. The rest comes from the trust itself and from the Frimley Health Charity Fleet Legacy Fund, which together cover the full programme of works.
What it means for you
If you have physio, a community nursing appointment or an outpatient clinic at Fleet, you should still be seen there while the building work goes on. The trust said: “The work will be carried out in phases to minimise disruption and allow clinical services to continue throughout.”
Once finished, the trust says the changes “will help services reduce wait times, while supporting additional community clinics and group sessions, and providing a more welcoming check-in experience.”
It added that the improved building “will also help colleagues make better use of the site and support the delivery of more care within the local community.”
The trust says it will share further updates as the plans progress, including what patients can expect while work is under way.
Source: Frimley Health NHS Foundation Trust.