County highways officers cannot yet recommend the Copse Farm composting plan at Eversley. They want lorry, junction and crash data first. Hart does not object in principle.
Hampshire County Council’s highways officers say they cannot make a recommendation on the Copse Farm composting plan at Eversley until the applicant sends more information. Their response, dated 10 November, asks for detail on the A327 junction, the lorry numbers, the bridleway the lorries would share and recent crash records.
Collard Group wants to compost up to 10,000 tonnes of garden and green waste a year on 1.7 hectares of the farm, off the A327 south of Eversley. The county decides the application, reference HCC/2026/0644, because it is a waste development. The response is on the county’s planning register.
Overview
- No highways recommendation yet. The county’s highways team says it is “unable to make a recommendation until the information set out above has been provided”.
- Hart District Council raises no objection in principle, as long as the county is satisfied on highways, drainage, ecology and the effect on neighbours.
- No decision date. Natural England’s request for a habitats assessment, made in October, is also still outstanding.
What the highways officers want
The farm is reached from the A327 along the Wood Farm access road, which is also a public bridleway. The response asks the applicant for:
- evidence of how the bridleway is used now, and how lorries and riders or walkers would be kept apart
- drawings of the A327 junction showing whether the largest lorries can turn in and out without crossing into the opposite lane
- a worst-case figure for the most lorries in a day during the busiest periods, and how the green waste varies by season
- collision records for the most recent five years, because the figures supplied, for April 2019 to March 2024, are more than two years old
The officers also describe what they saw at the junction. They say it “does not appear to have sufficient radii” for larger vehicles to turn. They point to the kerb on the south side of the access, which is being driven over. And they say mud on the road opposite the access “may indicate” that larger vehicles cannot turn wholly within their own lane.
The applicant’s swept path drawing covers a 10.2-metre tipper lorry turning from the farm track into the site, but not the turn off the A327 itself, the response says.
The numbers they accepted
Not everything is in question. The officers say sight lines of 2.4 metres by 147 metres can be achieved in both directions at the A327 junction, in line with the speeds recorded there.
They also accept the applicant’s traffic count. It recorded 85th percentile speeds, the speed most drivers stay under, of 49.6mph northbound and 48.6mph southbound on the 50mph road. Lorries make up around 3% of traffic.
The applicant’s estimate of lorry trips stands as a starting point:
| Measure | Applicant’s figure |
|---|---|
| Average load | 6 tonnes |
| Deliveries a year | about 1,667 |
| Deliveries a working day | 6 to 7 |
| Lorry movements a working day | 12 to 14 |
The officers say some days will see several deliveries and others none, which is why they want the busiest-day figure as well as the average.
What Hart said
Hart District Council is only a consultee. In its letter of 22 October it says it “raises no objection in principle”. It adds that the county must be satisfied on waste policy, highways, drainage, ecology and environmental impacts.
Hart says it particularly wants to be sure the plan does not harm “the character of the countryside, or the amenities of neighbouring residential occupiers through noise, odour, dust or other emissions”.
Where the application stands
Eversley Parish Council objected in October, citing the extra lorries on the A327 and the B3272 and the primary school nearby. Natural England said in October that the plan could affect the Thames Basin Heaths and two nearby Sites of Special Scientific Interest. It wants a habitats assessment before it can advise. The Environment Agency, the county’s flood team and Farnborough Airport do not object. Our earlier report sets out each response and what the plan includes.
No public comments had been published on the register by 20 November.
What it means for you
- Nothing is decided. The county will wait for the applicant’s reply to the highways officers and to Natural England before it can reach a decision.
- If you ride or walk the Wood Farm bridleway, the highways team has asked the applicant to show how it is used now. The comment period closed on 22 October; the case officer’s contact details are on the register page if you want to ask whether late comments will be read.
- If you drive the A327 south of Eversley, the junction layout and the lorry numbers are now the main open questions on highways.
Sources
- Hampshire County Council highways development planning response to application 26/01704/HCC, 10 November 2026, on the county planning register, for every highways point above. The register sits behind a disclaimer page.
- Hart District Council letter to Hampshire County Council, reference 26/01706/ADJ, 22 October 2026, on the same register.
- The applicant’s planning and transport statements and the October consultee responses, as set out in our first report.